Transmission Projects

Transmission lines carry high voltage electricity from generation facilities to your local substation. From there, smaller distribution lines carry power to your home.

PEC owns and maintains about 304 miles of transmission line. As our Hill Country community continues to grow, our system grows, too.

Maintaining and improving our transmission equipment is a mainstay of our commitment to delivering low-cost, reliable, and safe energy solutions.

Current transmission projects:

PEC will replace 11.25 miles of the existing wood pole 69 kV transmission line between the Blanco Substation and Mountain Top Substation in Blanco County with a single circuit 138kV line. The project aims to convert the 69kV line to 138kV, increasing its capacity and reliability.

Construction is scheduled to start in the summer of 2025 and be completed in the winter of 2025.

PEC will rebuild and upgrade the existing 6.2-mile 138 kV transmission line that connects the Trading Post substation to the Cedar Valley substation. Upgrades are scheduled to begin in the fall of 2023 and are estimated to be completed by April of 2025.

The purpose of this project is to upgrade the transmission line to meet the structural strength requirements outlined by the National Electrical Safety Code and increase the capacity of the transmission line. The upgrade includes replacing 6.2 miles of conductor and structures along the transmission line.

The new larger conductors will increase the capacity of the transmission system serving PEC members and other electric consumers in Central Texas. This project will help meet the area’s growing demand for electrical power, improve system reliability, and reduce ongoing maintenance costs.

The existing shield wire, which protects the transmission lines from lightning, will also be replaced with an optical ground wire to enable improved relay coordination and supervisory control of substations. The existing structures will be replaced with new steel monopoles that are typically 90-120 feet tall and have ground line diameters of approximately 5 feet. Some large-angle poles, generally used when the line shifts direction, can have ground line diameters of up to 12 feet and can be up to 120 feet above ground.

PEC is rebuilding the wood H-Frame portion of the existing 4.25 mile 138kV transmission line that connects the Buda substation to the Turnersville substation in Hays County. This project is to improve the reliability of the transmission line.

Construction is scheduled to start in fall of 2024 and be complete winter of 2025.

Search