Transmission Projects

Transmission lines carry high voltage electricity from generation facilities to your local substation. From there, smaller distribution lines carry power to your home.

PEC owns and maintains about 304 miles of transmission line. As our Hill Country community continues to grow, our system grows, too.

Maintaining and improving our transmission equipment is a mainstay of our commitment to delivering low-cost, reliable, and safe energy solutions.

Current transmission projects:

PEC is upgrading approximately 4.5 miles of the existing transmission line between the Friendship substation and Rutherford substation in Hays County. This project will help meet the area’s growing demand for electrical power, improve system reliability, and reduce current ongoing maintenance costs.

Transmission line upgrade construction is estimated to begin in July 2026 and is expected to be completed by March 2027. Construction activities will include preparing the site for heavy equipment such as bucket trucks and cranes, as well as digging holes, setting and removing poles, and installing new wire. Upgrades will take place within existing PEC easement areas. Due to our updated design, the new poles/structures will be placed in adjusted locations within the easement.

Click here to access frequently asked questions. 

PEC is modernizing approximately 2 miles of the existing transmission line between the Buda substation and Manchaca substation in Hays and Travis counties. Phase 1 of this project extends from the Manchaca substation southward to the vicinity of FM 967.

Construction is estimated to begin in January 2027 and is expected to be completed by June 2027.

Click here to access frequently asked questions. 

What is a right of way?

A transmission line right of way is the strip of land used to construct, operate, maintain, and repair transmission lines and facilities. Learn more about rights of way here.